LK 93 Trzebinia - Oświęcim
Four railway viaducts consist of prefabricated ABM FRAME system elements, and one structure consists of ABM ARCH elements and prefabricated retaining walls. All structures have been adapted for half-assembly while maintaining railway traffic on one of the tracks.
- km 16+353, km 21+203, km 4+536, km 6+932:
- Type of construction: ABM FRAME
- Type: Railway
- Assembly time:2 dni / obiekt
- Horizontal light:12,5 – 13,5 m
- Length: 10 - 11,5 m
- km 2+685:
- Type of construction: ABM ARCH
- Type: Railway
- Assembly time:2 dni
- Horizontal light:6,5 m
- Length:32,6 m