S19 Lublin - Lubartów

Two animal passages, PZGd-16 and PZGd-17, two railway tunnels, T-12 and T-22, and a road viaduct, WS-25. Each of the structures was made of prefabricated elements of the ABM ARCH system.

  • PZGd-16:
  • Type of construction: ABM ARCH
  • Type: Road
  • Assembly time:10 dni
  • Horizontal light:15,8 m
  • Length:81,82 m
  • PZGd-17:
  • Type of construction: ABM ARCH
  • Type: Road
  • Assembly time:5 dni
  • Horizontal light:19,5 m
  • Length:51,44 m
  • T-12:
  • Type of construction: ABM ARCH
  • Type: Road
  • Assembly time:10 dni
  • Horizontal light:16,6 m
  • Length:100,4 m
  • T-22:
  • Type of construction: ABM ARCH
  • Type: Road
  • Assembly time:12 dni
  • Horizontal light:8,44 m
  • Length:194,98 m
  • WS-25:
  • Type of construction: ABM ARCH
  • Type: Road
  • Assembly time:5 dni
  • Horizontal light:14,01 m
  • Length:43,72 m